[EventId:202411161200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 November 2024 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 November 2024.
Refer to market notice: 120523
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 16 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411160905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 November 2024 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 16 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 16 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Saturday, 16 November 2024
NON-CONFORMANCE NSW1 Region Saturday, 16 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 16/11/2024 07:10 to 16/11/2024 07:35
Amount: -7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411151955_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 November 2024 19:55
Issued by Australian Energy Market Operator Ltd at 1955 hrs on 15 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 November 2024.
Refer to market notice: 120505
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1955 hrs on 15 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411151655_review] Prices for interval 15-Nov-2024 16:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411151650_review] Prices for interval 15-Nov-2024 16:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411151645_review] Prices for interval 15-Nov-2024 16:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411151640_review] Prices for interval 15-Nov-2024 16:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Nov-2024 16:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411151630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 November 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 15 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.