Filter by category
Filter by Date
[EventId:202411010835_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 November 2024 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 1 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0835 hrs on 1 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410311700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 31 October 2024 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 31 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 October 2024.
Refer to market notice: 119705
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 31 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410311535_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 31 October 2024 15:35
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 31 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 31 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1535 hrs on 31 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Wagga B 330 kV Bus - NSW region - 31/10/2024
Inter-regional transfer limit variation - Wagga B 330 kV bus- NSW region - 31/10/2024
At 0028 hrs 31/10/2024 there was an unplanned outage of Wagga B 330 kV bus.
The following constraint set(s) invoked at 0045 hrs 31/10/2024
N-WAGGA_330_BUSB, N-JNWG_RADIAL, V-DBUSS_L and V-DBUSS_T
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024
Inter-regional transfer limit variation - Moorabool - Sydenham No.1 500 kV line - VIC region - 30/10/2024
A planned outage of Moorabool - Sydenham No.1 500 kV line in the VIC region was scheduled from 0500 hrs 22/10/2024 to 1930 hrs 01/11/2024.
The outage has been completed and Moorabool - Sydenham No.1 500 kV line returned to service at 1815 hrs 30/10/2024
Constraint set revoked: V-MLSY_NOEMTT_R
Manager NEM Real Time Operations
[EventId:202410301600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 October 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 30 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 October 2024.
Refer to market notice: 119683
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 30 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410301505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 October 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 30 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 30 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410291745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 17:45
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Refer to market notice: 119664
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410291710_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 17:10
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1710 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.