Market Notices

118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118342GENERAL NOTICE20/09/2024 04:43:35 PM

Update - Lightning vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region

Refer to AEMO Electricity Market Notice 118320 ,118321, 118322

At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.

Manager NEM Real Time Operations
118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
118301INTER-REGIONAL TRANSFER17/09/2024 12:21:32 PM

Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024

At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.

The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
118271INTER-REGIONAL TRANSFER14/09/2024 01:26:46 PM

Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024

At 1320 hrs 14/09/2024 there was a short notice outage of Braemar No2 330 kV / 275 kV Transformer.

The following constraint set(s) invoked at 1320 hrs 14/09/2024
Q-BRTX2

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
118269INTER-REGIONAL TRANSFER13/09/2024 03:57:07 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024

A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.

The outage has been completed and Armidale - Sapphire 8E 330 KV Line returned to service at 1600 hrs 13/09/2024

Constraint set(s) revoked: N-ARSR_8E, N-TW_SVC

Manager NEM Real Time Operations
118261INTER-REGIONAL TRANSFER13/09/2024 11:39:13 AM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024


A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.

The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.


Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
118252INTER-REGIONAL TRANSFER12/09/2024 12:40:03 PM

Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024

A planned outage of Murraylink in the SA region was scheduled from 1030 hrs 12/09/2024 to 1630 hrs 12/09/2024.

The outage has been completed and Murraylink returned to service at 1235 hrs 12/09/2024

Constraint set(s) revoked: I-MURRAYLINK

Manager NEM Real Time Operations
118251INTER-REGIONAL TRANSFER12/09/2024 12:33:53 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 12/09/2024


A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 0900 hrs 16/09/2024.

The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.


Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm