STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119318 has been updated at 1400 hrs 25/10/2024 to the following:
From 1800 hrs to 1900 hrs 28/10/2024.
The forecast capacity reserve requirement is 1059 MW.
The minimum capacity reserve available is 1027 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119321 is cancelled at 1400 hrs 25/10/2024.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 24/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119351 is cancelled at 1815 hrs 24/10/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/10/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119311 has been updated at 1750 hrs to the following:
[1.] From 1800 hrs 24/10/2024 to 1930 hrs 24/10/2024.
The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 1292 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119263 is cancelled at 1650 hrs 24/10/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
At 1435 hrs 24/10/2024 there was an unplanned outage of Directlink cable 1 and cable 3 (note cable 2 was on a prior outage).
The following constraint set(s) invoked at 1445 hrs 24/10/2024
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
From 1830 hrs to 1900 hrs 30/10/2024.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 1120 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
From 1800 hrs to 1900 hrs 29/10/2024.
The forecast capacity reserve requirement is 1040 MW.
The minimum capacity reserve available is 995 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region 28/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1730 hrs to 1800 hrs 28/10/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 768 MW.
[2.] From 1900 hrs to 2030 hrs 28/10/2024.
The forecast capacity reserve requirement is 1052 MW.
The minimum capacity reserve available is 673 MW.
AEMO Operations