[EventId:202411251625_review] Prices for interval 25-Nov-2024 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411251620_review] Prices for interval 25-Nov-2024 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411251615_review] Prices for interval 25-Nov-2024 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411251610_review] Prices for interval 25-Nov-2024 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411251605_review] Prices for interval 25-Nov-2024 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
INC0138597 - ALERT - EMMS
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 22/11/2024 22:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120843
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 22/11/2024 22:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120842
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/11/2024 21:24 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations