114607LOAD SHED13/02/2024 02:35:06 PM

Load Shedding Direction in the Vic Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the Vic Region

AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
114436INTER-REGIONAL TRANSFER08/02/2024 10:24:54 AM

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line


The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114429INTER-REGIONAL TRANSFER07/02/2024 07:06:39 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114407INTER-REGIONAL TRANSFER06/02/2024 09:12:48 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC

The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113654INTER-REGIONAL TRANSFER23/01/2024 03:30:39 AM

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.

The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113416INTER-REGIONAL TRANSFER18/01/2024 03:14:09 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 3 Leg of Directlink .

The following constraint set was invoked at 1510 hrs 18/01/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
113395INTER-REGIONAL TRANSFER17/01/2024 09:40:50 PM

Inter-regional transfer limit variation - Bulli Creek - Dumaresq 8M 330 kV line - QLD region - 17/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bulli Creek - Dumaresq 8M 330 kV line - QLD region - 17/01/2024

At 2115 hrs 17/01/2024 there was an unplanned outage of Bulli Creek - Dumaresq 8M 330 kV line.

The following constraint set(s) invoked at 2130 hrs 17/01/2024
I-BCDM_ONE, N-DM_SVC, N-TW_SVC, N-X_8L+DM+TW_SVC, N-X_DM+LS+TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113201INTER-REGIONAL TRANSFER11/01/2024 10:08:48 AM

Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024

At 0955 hrs 11/01/2024 there was an short notice outage of South East CB6611.

The following constraint set(s) invoked at 0955 hrs 11/01/2024
S-SECB6611_10

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113095INTER-REGIONAL TRANSFER07/01/2024 01:32:17 PM

Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024

At 1152 hrs 07/01/2024 there was an unplanned outage of the Crowlands-Bulgana-Horsham 220 kV Line.

The following constraint set invoked at 12:05 hrs 07/01/2024
V-CWHO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA
VIC1-NSW1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations