Market Notices

112155RECLASSIFY CONTINGENCY09/12/2023 10:59:35 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 09/12/2023 22:59

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 112136

Auto-generated on behalf of Manager NEM Real Time Operations
112136RECLASSIFY CONTINGENCY09/12/2023 03:57:50 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 09/12/2023 15:57 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
112131RECLASSIFY CONTINGENCY09/12/2023 01:18:47 PM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of Sheffield 220 kV switchyard (all 220 kV buses) in Tas due to planned work

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to planned work. AEMO considers the simultaneous trip of the following plant is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Plant: Sheffield 220 kV switchyard (all 220 kV buses)

Cancellation time: 09/12/2023 13:20 hrs

Constraint set revoked:
T-SH_220_N-2
Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1



Refer AEMO Electricity Market Notice 112089

Manager NEM Real Time Operations
112128RECLASSIFY CONTINGENCY09/12/2023 09:05:55 AM

Reclassification of a Non-Credible Contingency Event: Loss of Sheffield 220 kV switchyard (all 220 kV buses) in Tas due to planned work

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to planned work.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS

Plant: Sheffield 220 kV switchyard (all 220 kV buses)

Duration: 09/12/2023 : 0900 hrs until further notice

Constraint set(s) invoked: T-SH_220_N-2
Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1

Manager NEM Real Time Operations
112124RECLASSIFY CONTINGENCY09/12/2023 04:24:39 AM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 09/12/2023 04:24

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 112123

Auto-generated on behalf of Manager NEM Real Time Operations
112123RECLASSIFY CONTINGENCY09/12/2023 02:23:10 AM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 09/12/2023 02:23 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
112122RECLASSIFY CONTINGENCY08/12/2023 08:12:03 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 2015 hrs 08/12/2023
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 112054

Manager NEM Real Time Operations
112121RECLASSIFY CONTINGENCY08/12/2023 07:09:35 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 08/12/2023 19:09

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 112116

Auto-generated on behalf of Manager NEM Real Time Operations
112120GENERAL NOTICE08/12/2023 05:35:38 PM

Network Augmentation Commissioned - NSW Region - 08/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 08/12/2023

Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line

Manager NEM Real Time Operations