Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 11/12/2023 17:59
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 112189
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1530 hrs 14/12/2023 to 1700 hrs 14/12/2023.
The forecast capacity reserve requirement is 1088 MW.
The minimum capacity reserve available is 692 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Duration: 11/12/2023 16:58 until further notice
Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112179 is cancelled at 1400 hrs 11/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
Update - Non-credible contingency event - SA region - 11/12/2023
Update - Non-credible contingency event - SA region - 11/12/2023
Refer AEMO Electricity Market Notice 112170
Region: SA
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
At 1413 hrs the Clare North - Mintaro 132 kV Line was returned to service (RTS)
The following constraint set(s) invoked:
S-X-MNWT+CB
The following constraint set(s) revoked:
S-BR_MN+MN_WT
This constraint set(s) contains equations with the following interconnectors on the LHS:
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Non-credible contingency event - SA region - 11/12/2023
Update - Non-credible contingency event - SA region - 11/12/2023
Refer AEMO Electricity Market Notice 112165
Region: SA
The following constraint set(s) invoked:
Initially S-MNWT and S-MN_0 then replaced with S-BR_MN+MN_WT
This constraint set(s) contains equations with the following interconnectors on the LHS:
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Duration: 10/12/2023 15:45 hrs until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.
Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: SA
Lines: Para-Templers West and Magill-Torrens Island A 275kV lines
Duration: 10/12/2023 12:30 hrs until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations