121236RECLASSIFY CONTINGENCY29/11/2024 01:16:50 PM

Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Duration: 29/11/2024 13:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
121225PRICES SUBJECT TO REVIEW29/11/2024 07:05:17 AM

[EventId:202411290710_review] Prices for interval 29-Nov-2024 07:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0705 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121224PRICES SUBJECT TO REVIEW29/11/2024 07:00:19 AM

[EventId:202411290705_review] Prices for interval 29-Nov-2024 07:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0700 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121222PRICES SUBJECT TO REVIEW29/11/2024 06:55:23 AM

[EventId:202411290700_review] Prices for interval 29-Nov-2024 07:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0655 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 07:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121221PRICES SUBJECT TO REVIEW29/11/2024 06:50:18 AM

[EventId:202411290655_review] Prices for interval 29-Nov-2024 06:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0650 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121220PRICES SUBJECT TO REVIEW29/11/2024 06:45:21 AM

[EventId:202411290650_review] Prices for interval 29-Nov-2024 06:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0645 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121219PRICES SUBJECT TO REVIEW29/11/2024 06:40:18 AM

[EventId:202411290645_review] Prices for interval 29-Nov-2024 06:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0640 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 06:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121218RESERVE NOTICE29/11/2024 05:26:03 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121217 is cancelled at 0525 hrs 29/11/2024.

Manager NEM Real Time Operations
     
121217RESERVE NOTICE29/11/2024 05:00:17 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121216 has been updated at 0500 hrs to the following:

[1.] From 1430 hrs 29/11/2024 to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1428 MW.

Manager NEM Real Time Operations
     