Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024
Inter-regional transfer limit variation - Para - Roseworthy 132 kV Line - SA region - 01/03/2024
At 1515 hrs 01/03/2024 there was a short notice outage of Para - Roseworthy 132 kV Line.
The following constraint set was invoked at 1530 hrs 01/03/2024
S-PARS
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024
Inter-regional transfer limit variation - Mt Piper 500/330 kV TIE1 Transformer - NSW region - 01/03/2024
At 0747 hrs 01/03/2024 there was an unplanned outage of Mt Piper 500/330 kV TIE1 Transformer.
Constraint set(s) invoked: N-MPTX
The following constraint set(s) invoked at 0755 hrs 01/03/2024
N-MPTX
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations