Market Notices

116637SETTLEMENTS RESIDUE16/05/2024 05:30:33 PM

[EventId:202405161730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 May 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 16 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
116616RESERVE NOTICE14/05/2024 06:24:48 PM

Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024

The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.

Manager NEM Real Time Operations
116615RESERVE NOTICE14/05/2024 05:43:15 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1800 hrs.

The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.


Manager NEM Real Time Operations
116567RESERVE NOTICE09/05/2024 07:15:54 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.

Manager NEM Real Time Operations
116566RESERVE NOTICE09/05/2024 05:13:13 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW

Manager NEM Real Time Operations
116551SETTLEMENTS RESIDUE08/05/2024 08:30:22 PM

[EventId:202405082030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 20:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2030 hrs on 8 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Refer to market notice: 116542

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 8 May 2024.

This is an AEMO autogenerated Market Notice.
116548RESERVE NOTICE08/05/2024 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116547RESERVE NOTICE08/05/2024 05:45:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1417 MW

Manager NEM Real Time Operations
116542SETTLEMENTS RESIDUE08/05/2024 03:30:23 PM

[EventId:202405081530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 8 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 8 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.