Market Notices

112859INTER-REGIONAL TRANSFER29/12/2023 01:58:35 AM

Inter-regional transfer limit variation - Para No.1 275 kV SVC - SA region - 29/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Para No.1 275 kV SV - SA region - 29/12/2023

At 0145 hrs 29/12/2023 there was a short notice outage of Para No.1 275 kV SVC.

The following constraint set(s) invoked at 0145 hrs 29/12/2023
S-PA_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112858INTER-REGIONAL TRANSFER28/12/2023 09:43:00 PM

Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West - Munno Para 275 kV line - SA region - 28/12/2023

At 2115 hrs 28/12/2023 there was an unplanned outage of the Blyth West - Munno Para 275 kV line.

The following constraint set(s) invoked at 2125 hrs 28/12/2023
S-BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112854INTER-REGIONAL TRANSFER28/12/2023 07:32:53 PM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 28/12/2023

At 1913 hrs 28/12/2023 there was an unplanned outage of the Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 1925 hrs 28/12/2023
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112853INTER-REGIONAL TRANSFER28/12/2023 07:07:21 PM

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

Refer AEMO Electricity Market Notice 112852.

Constraint set CA_SYDS_549FBEF5 revoked 1850 hrs.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1


Manager NEM Real Time Operations
112852INTER-REGIONAL TRANSFER28/12/2023 06:44:09 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 28/12/2023

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYDS_549FBEF5 from 1830 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
112818NON-CONFORMANCE27/12/2023 02:45:22 PM

NON-CONFORMANCE Region NSW1 Wednesday, 27 December 2023

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 27 December 2023

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 27/12/2023 14:35 to 27/12/2023 14:45
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
112784INTER-REGIONAL TRANSFER26/12/2023 07:10:58 PM

Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Pelican Point Circuit Breaker 8093 - SA region - 26/12/2023

At 1832 hrs 26/12/2023 there was a short notice outage of Pelican Point Circuit Breaker 8093.

The following constraint set(s) invoked at 1855 hrs 26/12/2023
S-PPT_CB6727

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112759INTER-REGIONAL TRANSFER26/12/2023 07:37:06 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0735 hrs 26/12/2023

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for return to service details

Manager NEM Real Time Operations
112746INTER-REGIONAL TRANSFER25/12/2023 09:46:39 PM

Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023

At 2102 hrs 25/12/2023 there was an unplanned outage of Greenbank - Mudgeeraba 835 275 kV line

Constraint set(s) invoked: Q-GBMU_835_836 from 2105 hrs

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations