Filter by category
Filter by Date
Inter-regional transfer limit variation - [outage element] - NSW region - 04/07/2024
Inter-regional transfer limit variation - Lismore - Dunoon 9U7 132 kV line - NSW region - 04/07/2024
A planned outage of Lismore - Dunoon 9U7 132 kV line in the NSW region was scheduled from 0732 hrs 02/07/2024 to 1700 hrs 19/07/2024.
The outage has been completed and Lismore - Dunoon 9U7 132 kV line returned to service at 1105 hrs 04/07/2024
Constraint set(s) revoked: N-LSDU_9U6
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.
Refer to market notice: 117283
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Dumaresq No. 1 330kV SVC - NSW region - 28/06/2024
Inter-regional transfer limit variation - Dumaresq No. 1 330kV SVC- NSW region - 28/06/2024
At 1649 hrs 28/06/2024 there was a short notice outage of the Dumaresq No. 1 330kV SVC.
The following constraint set invoked at 1650 hrs 28/06/2024
N-DM_SVC
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
Refer AEMO Electricity Market Notice 117239.
Constraint set CA_SYDS_5590C0E2 revoked 1530 hrs.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024
Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024
At 1407 hrs 28/06/2024 there was an unplanned outage of Liddell to Tomago 82 330kV Line.
The following constraint set invoked at 1415 hrs 28/06/2024
N-LDTM_82_OPEN
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_5590C0E2 from 1355hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/06/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/06/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0815 hrs 26/06/2024 to 1930 hrs 26/06/2024.
The outage has been completed and Heywood - South East No 2 275 kV Line returned to service at 1410 hrs 26/06/2024
Constraint set(s) revoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024
A planned outage of Hazelwood - South Morang No 1 500 kV Line in the VIC region was scheduled from 0800 hrs 25/06/2024 to 1530 hrs 25/06/2024.
The outage has been completed and Hazelwood - South Morang No 1 500 kV Line returned to service at 1016 hrs 25/06/2024
Constraint set(s) revoked: V-HWSM
Manager NEM Real Time Operations