116575MARKET SYSTEMS10/05/2024 02:49:28 PM

CHG0089536 | Production | Urgent NSW Marketnet Router Replacement

Change Number: CHG0089536

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: Urgent NSW Marketnet Router Replacement

Change Start Date & Time: 11/05/2024 10:00:27 AEST
Change End Date & Time: 11/05/2024 14:00:27 AEST
Outage Start Date & Time: 11/05/2024 10:00:26 AEST
Outage End Date & Time: 11/05/2024 12:00:26 AEST

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from NSW to QLD Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.

GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116563MARKET SYSTEMS09/05/2024 03:10:22 PM

CHG0089532 | Cancelled | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Change Number: CHG0089532

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 11.00am Thursday 9 May until 1pm (EST)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
116560MARKET SYSTEMS09/05/2024 11:07:46 AM

CHG0089539 | Production | QLD Internet Router Refresh

Change Number: CHG0089539

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Internet Access

Change Title: QLD Internet Router Refresh

Change Start Date & Time: 25/05/2024 09:00:08 AEST
Change End Date & Time: 25/05/2024 14:00:08 AEST
Outage Start Date & Time: 25/05/2024 09:30:21 AEST
Outage End Date & Time: 25/05/2024 13:00:21 AEST

Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only

SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.

GASHUB: No impact is expected as GASHUB is currently operating out of NOR Datacenter.

Other Impacts will have been communicated in advance.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
116549RESERVE NOTICE08/05/2024 07:22:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116545RESERVE NOTICE08/05/2024 05:19:39 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
116504MARKET SYSTEMS07/05/2024 12:34:27 PM

CHG0087670 | Completed | Production | MSATS-CATS Production Maintenance

Change Number: CHG0087670

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
116503RESERVE NOTICE07/05/2024 12:01:42 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.

No LOR2 condition is currently forecast in the STPASA period.


AEMO Operations
116502RESERVE NOTICE07/05/2024 10:02:31 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

116455MARKET SYSTEMS03/05/2024 03:09:17 PM

CHG0088386 | Cancelled | Production | QLD Internet Router Refresh

Change Number: CHG0088386
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: Internet Access
Change Title: QLD Internet Router Refresh

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm