Filter by category
Filter by Date
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 27/11/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121089 has been updated at 1645 hrs to the following:
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 859 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121069 has been updated at 1530 hrs to the following:
[1.] From 1430 hrs 28/11/2024 to 1930 hrs 28/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1108 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121066 is cancelled at 1530 hrs 27/11/2024.
Manager NEM Real Time Operations
AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy
AEMO Intervention Event - Intervention price dispatch intervals - dd/mm/yyyy
Refer AEMO Electricity Market Notice no. 121100
An AEMO Intervention Event, the dispatch of Reliability and Emergency Reserve Trader (RERT) has been implemented.
The AEMO Intervention Event commenced at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event is expected to affect dispatch quantities for intervention pricing purposes from the 15:50 hrs dispatch interval on 27/11/2024
Manager NEM Real Time Operations
RERT DISPATCHED
AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - NSW1 Region- 27/11/2024
Refer AEMO Electricity Market Notice no. 121054
AEMO has dispatched/activated reserve contract(s) to maintain the power system in a Reliable operating state.
The reserve contract(s) was dispatched/activated at 15:45 hrs 27/11/2024 and is forecast to apply until 18:00 hrs 27/11/2024
AEMO has implemented an AEMO intervention event for the duration the reserve contract(s) is dispatched/activated/
To facilitate the RERT process, constraints commencing with the following identifiers may be evident at various times in dispatch,
#RT_NSW1
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 26/11/2024
Cancellation - AEMO Intervention Event - SA region 26/11/2024
Refer to Market Notice 121002
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 27/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121096
Direction is cancelled from: 1700 hrs 27/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 121031
Direction is cancelled from: 1700 hrs 27/11/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121048
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 27/11/2024.
The direction update is issued at 1620 hrs 27/11/2024.
Manager NEM Real Time Operations