Filter by category
Filter by Date
CHG0100257 | Production | MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services.
Change Start Date & Time: 12/12/2024 14:00:00 AEST
Change End Date & Time: 12/12/2024 16:00:00 AEST
Outage Start Date & Time: 12/12/2024 15:00:00 AEST
Outage End Date & Time: 12/12/2024 15:01:00 AEST
Environment: Production
Participant Impact and Requirements: During there change, there will be a 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Norwest will not be affected during this time.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 920 MW.
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 08/12/2024
Cancellation - Forecast MSL1 - VIC Region at 1230 hrs 08/12/2024.
Refer to Market Notice 121617 for Forecast MSL1.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024
Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024
Update to Market Notice 121508 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 08/12/2024.
Minimum regional demand is forecast to be 1299 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1560 MW
o MSL2 - 1060 MW
o MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1130 hrs 08/12/2024 to 1400 hrs 08/12/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121608 is cancelled at 2020 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1900 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 944 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121588 is cancelled at 1415 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 07/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121585 is cancelled at 1300 hrs 07/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 08/12/2024 to 1930 hrs 08/12/2024.
The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 807 MW.
Manager NEM Real Time Operations