Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117017 is cancelled at 1400 hrs 16/06/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 21/06/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No 117008 and No 1170016 is cancelled at 1400 hrs 16/06/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116979 has been updated at 1500 hrs 15/06/2024 to the following:
[1.]From 1530 hrs 19/06/2024 to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1398 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117006 has been updated at 1500 hrs 15/06/2024 to the following:
(1.] From 0530 hrs 19/06/2024 to 1000 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1428 MW.
[2.] From 1530 hrs 19/06/2024 to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1398 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116999 has been updated at 1500 hrs 15/06/2024 to the following:
[1.] From 0630 hrs 18/06/2024 to 0830 hrs 18/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1696 MW.
[2.] From 1630 hrs 18/06/2024 to 0100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1687 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 21/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1800 hrs 21/06/2024 to 2130 hrs 21/06/2024.
The forecast capacity reserve requirement is 421 MW.
The minimum capacity reserve available is 393 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117011 has been updated at 1500 hrs to the following:
From 1730 hrs 15/06/2024 to 1830 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1650 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.116990 has been updated at 1713 hrs to the following:
[1.] From 1700 hrs 15/06/2024 to 1830 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1572 MW.
Manager NEM Real Time Operations
CHG0090646 | Production | Planned maintenance affecting the AEMO Market Network.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 24/06/2024 09:30:00 AEST
Change End Date & Time: 24/06/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 24th of June 2024, between 07:30AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Sydney.
No outage or impact is expected, however AEMO recommends that all market participants with site to site VPN connections currently connected via Sydney, to switch these connections to the Brisbane site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Brisbane site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .