Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
Refer AEMO Electricity Market Notice 117239.
Constraint set CA_SYDS_5590C0E2 revoked 1530 hrs.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024
Inter-regional transfer limit variation - Liddell to Tomago 82 330kV Line - NSW region - 28/06/2024
At 1407 hrs 28/06/2024 there was an unplanned outage of Liddell to Tomago 82 330kV Line.
The following constraint set invoked at 1415 hrs 28/06/2024
N-LDTM_82_OPEN
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 28/06/2024
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_5590C0E2 from 1355hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
CHG0090919 | Completed | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market (STTM)
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090782 | Completed | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090805 | Completed | Production | Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/06/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/06/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0815 hrs 26/06/2024 to 1930 hrs 26/06/2024.
The outage has been completed and Heywood - South East No 2 275 kV Line returned to service at 1410 hrs 26/06/2024
Constraint set(s) revoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Manager NEM Real Time Operations
CHG0090725 | Completed | Pre-Production | Pre-Prod MSATS and eMDM July Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS and eMDM July Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090802 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.