Filter by category
Filter by Date
[EventId:202411221110_confirmed] Prices for interval 22-Nov-2024 11:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1117 hrs on 22 November 2024
PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:10.
In accordance with Market Notice 120794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $150.01 $25.81
QLD1 $143.43 $26.90
SA1 $53.81 $11.91
VIC1 $55.02 $12.00
LOWER5MIN
NSW1 $1.57 $0.39
QLD1 $1.57 $0.39
SA1 $1.57 $0.39
VIC1 $1.57 $0.39
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $20.90 $19.85
QLD1 $20.90 $19.85
SA1 $20.90 $19.85
VIC1 $20.90 $19.85
RAISE1SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
TAS1 $0.10 $0.05
VIC1 $0.10 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.05 $0.01
QLD1 $0.05 $0.01
SA1 $0.05 $0.01
VIC1 $0.05 $0.01
RAISE6SEC
NSW1 $0.10 $0.00
QLD1 $0.10 $0.00
SA1 $0.10 $0.00
VIC1 $0.10 $0.00
RAISEREG
NSW1 $5.00 $1.00
QLD1 $5.00 $1.00
SA1 $5.00 $1.00
VIC1 $5.00 $1.00
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Friday, 22 November 2024
NON-CONFORMANCE NSW1 Region Friday, 22 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 22/11/2024 08:05 to 22/11/2024 08:25
Amount: -73 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Cancellation - AEMO Intervention Event - SA region 15/11/2024
Refer to Market Notice 120499
The AEMO Intervention Event and all associated directions are cancelled from 1335 hrs on 21/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 120723
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120722
Direction is cancelled from: 1330 hrs 21/11/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 21 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 21 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 21/11/2024 01:55 to 21/11/2024 02:10
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 21/11/2024
Network Augmentation Commissioned - QLD Region - 21/11/2024
Commissioned:
Belmont No.2 275 kV 150 MVar reactor
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120680
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120679
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.
The direction update is issued at 1630 hrs 20/11/2024.
Manager NEM Real Time Operations