120722MARKET INTERVENTION20/11/2024 04:28:21 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120679

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1330 hrs 21/11/2024.

The direction update is issued at 1630 hrs 20/11/2024.

Manager NEM Real Time Operations
     
120682INTER-REGIONAL TRANSFER19/11/2024 04:44:40 PM

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.

The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024

Constraint set(s) revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
120680MARKET INTERVENTION19/11/2024 04:58:32 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120625

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/11/2024.

The direction update is issued at 1700 hrs 19/11/2024.

Manager NEM Real Time Operations
     
120679MARKET INTERVENTION19/11/2024 04:56:17 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120626

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/11/2024.

The direction update is issued at 1700 hrs 19/11/2024.

Manager NEM Real Time Operations
     
120636MARKET INTERVENTION18/11/2024 06:24:54 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120609

Direction is cancelled from: 1830 hrs 18/11/2024

Manager NEM Real Time Operations
     
120626MARKET INTERVENTION18/11/2024 04:33:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120553

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/11/2024.

The direction update is issued at 1630 hrs 18/11/2024.

Manager NEM Real Time Operations
     
120625MARKET INTERVENTION18/11/2024 04:37:54 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1630 hrs 18/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 19/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 20/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120616INTER-REGIONAL TRANSFER18/11/2024 04:02:01 PM

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024

At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.

The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120609MARKET INTERVENTION18/11/2024 10:22:46 AM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 120594

The MINTARO MINTARO GAS direction is now expected to stay in place until 1830 hrs 18/11/2024.

The direction update is issued at 1000 hrs 18/11/2024.

Manager NEM Real Time Operations
     