117486POWER SYSTEM EVENTS27/07/2024 10:26:53 AM

Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117286RESERVE NOTICE03/07/2024 08:10:15 PM

Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.

Manager NEM Real Time Operations
117284RESERVE NOTICE03/07/2024 05:42:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW

Manager NEM Real Time Operations
117210POWER SYSTEM EVENTS27/06/2024 09:01:59 AM

Non-credible contingency event - NSW region - 27/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 27/06/2024

At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117132POWER SYSTEM EVENTS25/06/2024 10:20:35 AM

Non-credible contingency event - NSW region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 25/06/2024

At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117087RESERVE NOTICE20/06/2024 07:41:48 PM

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 20/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117086 is cancelled at 1930hrs 20/06/2024.

Manager NEM Real Time Operations
117086RESERVE NOTICE20/06/2024 06:13:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1726 MW
The minimum capacity reserve available is 1695 MW

Manager NEM Real Time Operations
117042POWER SYSTEM EVENTS18/06/2024 10:16:34 AM

Non-credible contingency event - VIC region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 18/06/2024

At 0839 hrs the Glenrowan No1 66kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations