Market Notices

121085SETTLEMENTS RESIDUE27/11/2024 02:20:22 PM

[EventId:202411271420_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 November 2024 14:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Refer to market notice: 121081

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1420 hrs on 27 November 2024.

This is an AEMO autogenerated Market Notice.
     
121084RESERVE NOTICE27/11/2024 02:30:48 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121049 has been updated at 1420 hrs to the following:

[1.] From 1600 hrs 27/11/2024 to 1830 hrs 27/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 509 MW.

AEMO is seeking a market response.

AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1330 hrs on 27/11/2024.

Manager NEM Real Time Operations
     
121083MARKET INTERVENTION27/11/2024 02:18:44 PM

Direction - NSW region to Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

AEMO ELECTRICITY MARKET NOTICE

Direction - NSW region to Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1

Refer to Market Notice 121070


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Munmorah Battery ProjectCo Pty Ltd. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Munmorah Battery ProjectCo Pty Ltd - WARATAHBESS1 at 1415 hrs 27/11/2024
Type of resource: bi-directional unit
Required actions: Maintain 96 MWh Energy Storage Level and follow dispatch targets at 1500 hrs 27/11/2024
Services provided: Reserve
Circumstances necessitating the Direction: Reliability
Circumstances necessitating the Direction additional detail: intervention is required to maintain the reliability standard

Expected duration: 1900 hrs 27/11/2024.


Manager NEM Real Time Operations
     
121081SETTLEMENTS RESIDUE27/11/2024 01:32:33 PM

[EventId:202411271330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 November 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 27 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121074MARKET INTERVENTION27/11/2024 02:10:56 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 121059

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 28/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 27/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
121070MARKET INTERVENTION27/11/2024 01:30:03 PM

Direction - NSW region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - NSW region 27/11/2024

In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO has issued a direction to a participant in the NSW region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1335 hrs on 27/11/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
121067MARKET INTERVENTION27/11/2024 01:28:54 PM

Direction - NSW region to Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS

AEMO ELECTRICITY MARKET NOTICE

Direction - NSW region to Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS

Refer to Market Notice 121070.


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Iberdrola Australia Wallgrove Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Iberdrola Australia Wallgrove Pty Limited - WALLGROVE BESS at 1330 hrs 27/11/2024
Type of resource: bi-directional unit
Required actions: Maintain 59 MWh Energy Storage Level and follow dispatch targets at 1430 hrs 27/11/2024
Services provided: Reserve
Circumstances necessitating the Direction: Reliability
Circumstances necessitating the Direction additional detail: intervention is required to maintain the reliability standard

Expected duration: 1900 hrs 27/11/2024.


Manager NEM Real Time Operations
     
121066RESERVE NOTICE27/11/2024 01:03:57 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:

[1.] From 1500 hrs 28/11/2024 to 1600 hrs 28/11/2024.
The forecast capacity reserve requirement is 1176 MW.
The minimum capacity reserve available is 1026 MW.

[2.] From 1700 hrs 28/11/2024 to 1900 hrs 28/11/2024.
The forecast capacity reserve requirement is 1121 MW.
The minimum capacity reserve available is 351 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121062RESERVE NOTICE27/11/2024 12:57:26 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1730 hrs 28/11/2024 to 1830 hrs 28/11/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 351 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     