Market Notices

115779NON-CONFORMANCE25/03/2024 10:00:22 AM

NON-CONFORMANCE Region NSW1 Monday, 25 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 25 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 25/03/2024 09:15 to 25/03/2024 10:00
Amount: 20 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
115774GENERAL NOTICE25/03/2024 04:33:09 AM

Severe Space Weather Watch Notification 25/03/2024

AEMO ELECTRICITY MARKET NOTICE

Severe Space Weather Watch Notification 25/03/2024

The Australian Bureau of Meteorology's Space Weather Forecasting Centre has issued the following notification.

Severe space weather watch: A recent space weather event is anticipated to impact the Earth within the next 48 hours.

The effects are expected to be significant.

Increased awareness of critical infrastructure is advised.

Please monitor the SWS website for further updates at https://www.sws.bom.gov.au

If required; actions will be taken as per AEMO's system operating procedure SO_OP3715 Power System Security Guidelines.

Manager NEM Real Time Operations
115773NON-CONFORMANCE24/03/2024 09:10:11 PM

NON-CONFORMANCE Region VIC1 Sunday, 24 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 24 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 24/03/2024 21:05 to 24/03/2024 21:10
Amount: 58 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
115725NON-CONFORMANCE21/03/2024 09:10:21 AM

NON-CONFORMANCE Region NSW1 Thursday, 21 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 21 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 21/03/2024 06:50 to 21/03/2024 09:10
Amount: 22 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
115724NON-CONFORMANCE20/03/2024 07:25:13 PM

NON-CONFORMANCE Region QLD1 Wednesday, 20 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 20 March 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WANDBG1, WANDBL1
Aggregate Dispatch Group: WANDBESS_ADG1
Duration: 20/03/2024 18:30 to 20/03/2024 19:25
Amount: -42 MW
Constraint: NC-Q_WANDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
115675NON-CONFORMANCE17/03/2024 06:45:12 PM

NON-CONFORMANCE Region QLD1 Sunday, 17 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 17 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 17/03/2024 18:40 to 17/03/2024 18:45
Amount: 59 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
115673NON-CONFORMANCE17/03/2024 06:00:14 PM

NON-CONFORMANCE Region QLD1 Sunday, 17 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 17 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 17/03/2024 17:50 to 17/03/2024 18:00
Amount: -53 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
115656NON-CONFORMANCE16/03/2024 09:05:19 AM

NON-CONFORMANCE Region NSW1 Saturday, 16 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 16 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 16/03/2024 09:00 to 16/03/2024 09:05
Amount: 15 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
115654SETTLEMENTS RESIDUE15/03/2024 04:00:21 PM

[EventId:202403151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 March 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.

Refer to market notice: 115646

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 March 2024.

This is an AEMO autogenerated Market Notice.