Market Notices

120734RESERVE NOTICE20/11/2024 10:18:25 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120726 has been updated at 2200 hrs 20/11/2024 to the following:

From 1330 hrs 26/11/2024 to 2000 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 130 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120726RESERVE NOTICE20/11/2024 05:11:53 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120712 has been updated at 1600 hrs 20/11/2024 to the following:

1. From 1400 hrs to 1530 hrs 26/11/2024.
The forecast capacity reserve requirement is 699 MW.
The minimum capacity reserve available is 132 MW.

2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 149 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120724GENERAL NOTICE21/11/2024 12:37:48 PM

Network Augmentation Commissioned - QLD Region - 21/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/11/2024

Commissioned:

Belmont No.2 275 kV 150 MVar reactor

Manager NEM Real Time Operations
     
120714SETTLEMENTS RESIDUE20/11/2024 02:00:33 PM

[EventId:202411201400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 November 2024 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 20 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.

Refer to market notice: 120709

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 20 November 2024.

This is an AEMO autogenerated Market Notice.
     
120712RESERVE NOTICE20/11/2024 02:22:38 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120703 has been updated at 0900 hrs 20/11/2024 to the following:

From 1400 hrs to 2030hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120711RESERVE NOTICE20/11/2024 02:21:35 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120704 has been updated at 1300 hrs 20/11/2024 to the following:

From 1530 hrs to 1930 hrs 25/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 39 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120709SETTLEMENTS RESIDUE20/11/2024 12:40:25 PM

[EventId:202411201240_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 November 2024 12:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1240 hrs on 20 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1240 hrs on 20 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120707RESERVE NOTICE20/11/2024 12:17:20 PM

STPASA - Cancellation of the Forecast Lack of Reserve Level 2 (LOR2) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120705 is cancelled at 1100 hrs 20/11/2024.

AEMO Operations
     
120706GENERAL NOTICE20/11/2024 11:00:44 AM

Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120307

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs

This test includes includes a fast runback of Murraylink.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     