PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116556 is cancelled at 0840 hrs 09/05/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116555 has been updated at 0745 hrs to the following:
[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1416 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116552 has been updated at 0620 hrs to the following:
[1.] From 1630 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1320 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.116546 has been updated at 2015 hrs to the following:
[1.] From 1630 hrs 09/05/2024 to 1830 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1107 MW.
Manager NEM Real Time Operations
[EventId:202405082030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 May 2024 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 8 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Refer to market notice: 116542
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 8 May 2024.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116531 has been updated at 1720 hrs to the following:
[1.] From 1430 hrs 09/05/2024 to 1530 hrs 09/05/2024.
The forecast capacity reserve requirement is 1380 MW.
The minimum capacity reserve available is 1361 MW.
[2.] From 1600 hrs 09/05/2024 to 1730 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 874 MW.
[3.] From 1800 hrs 09/05/2024 to 1930 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 898 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116540 has been updated at 1620 hrs to the following:
[1.] From 1730 hrs 08/05/2024 to 1830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 1245 MW.
Manager NEM Real Time Operations
[EventId:202405081530_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 May 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 8 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1530 hrs on 8 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1700 hrs 08/05/2024 to 1900 hrs 08/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1125 MW.
Manager NEM Real Time Operations