118934MARKET SYSTEMS16/10/2024 03:56:26 PM

CHG0098812 | Completed | Pre-Production | Pre-Prod MSATS and eMDM November Maintenance Release

Change Number: CHG0098812

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Market Settlement & Transfer System

Change Title: Pre-Prod MSATS and eMDM November Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118930GENERAL NOTICE16/10/2024 12:49:48 PM

Heywood testing (Vic to SA) 16th October 2024

AEMO ELECTRICITY MARKET NOTICE

There is an opportunity for testing Heywood Interconnector (HIC) flow from Victoria to South Australia above 450MW on 16th October from 17:00hrs to 20:00hrs

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
118924GENERAL NOTICE16/10/2024 10:22:11 AM

NEM Local Temperature Alerts for SA from 16 Oct 2024 to 20 Oct 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 16th Oct, 17th Oct
The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
118911MARKET SYSTEMS15/10/2024 01:53:48 PM

CHG0098814 | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS and eMDM November Maintenance Release

Change Start Date & Time: 27/10/2024 10:00:00 AEST
Change End Date & Time: 27/10/2024 17:00:00 AEST
Outage Start Date & Time: 27/10/2024 10:00:00 AEST
Outage End Date & Time: 27/10/2024 14:00:00 AEST

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
     
118871GENERAL NOTICE14/10/2024 11:04:54 AM

NEM Local Temperature Alerts for SA from 14 Oct 2024 to 18 Oct 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 17th Oct

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
118771GENERAL NOTICE11/10/2024 08:25:55 AM

Heywood testing (SA to Vic) 11th October 2024

AEMO ELECTRICITY MARKET NOTICE

There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 11th October from 8:00hrs to 19:00hrs

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
118598MARKET SYSTEMS04/10/2024 04:07:21 PM

CHG0098496 | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .


     
118539MARKET SYSTEMS30/09/2024 05:41:19 PM

CHG0098133:NEM Reform - RMI (Retail Market Improvements) MSATS 54.0 - Completed

Change Number: CHG0098133
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118528GENERAL NOTICE30/09/2024 09:20:28 AM

Heywood testing (SA to Vic) 30th September 2024

AEMO ELECTRICITY MARKET NOTICE

There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 30th September from 9:00hrs to 17:00hrs

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations