STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0530 hrs to 0600 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1421 MW.
2. From 1600 hrs to 2230 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 807 MW.
AEMO Operations
[EventId:202405161745_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 May 2024 17:45
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.
Refer to market notice: 116637
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1745 hrs on 16 May 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202405161730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 May 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 May 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 May 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 16 May 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024
Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 116609 is cancelled at 1415 hrs 14/05/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116559 has been updated at 1615 hrs to the following:
[1.] From 1630 hrs 09/05/2024 to 1900 hrs 09/05/2024.
The forecast capacity reserve requirement is 1450 MW.
The minimum capacity reserve available is 979 MW.
Manager NEM Real Time Operations