120329NON-CONFORMANCE12/11/2024 07:20:19 PM

NON-CONFORMANCE Region VIC1 Tuesday, 12 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 12 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS2
Duration: 12/11/2024 19:10 to 12/11/2024 19:20
Amount: -23 MW
Constraint: NC-V_YWPS2

Auto-generated on behalf of Manager NEM Real Time Operations
     
120306POWER SYSTEM EVENTS12/11/2024 11:43:52 AM

Update - Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 12/11/2024

Refer AEMO Electricity Market Notice 120305

At 1135 hrs the Yallourn No 1 220 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
120305POWER SYSTEM EVENTS12/11/2024 10:55:18 AM

Non-credible contingency event - VIC region - 12/11/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 12/11/2024

At 1041 hrs the Yallourn No 1 220 kV bus and Yallourn Unit 4 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.


The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
120197NON-CONFORMANCE09/11/2024 09:10:15 PM

NON-CONFORMANCE Region VIC1 Saturday, 9 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 9 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 09/11/2024 20:55 to 09/11/2024 21:10
Amount: 9 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120179NON-CONFORMANCE09/11/2024 02:45:22 AM

NON-CONFORMANCE Region NSW1 Saturday, 9 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 09/11/2024 02:40 to 09/11/2024 02:45
Amount: -42 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
120149RESERVE NOTICE08/11/2024 03:13:21 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120138 is cancelled at 1510 hrs 08/11/2024.

Manager NEM Real Time Operations
     
120148RESERVE NOTICE08/11/2024 03:45:18 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120139 is cancelled at 1545 hrs 08/11/2024.

Manager NEM Real Time Operations
     
120142NON-CONFORMANCE08/11/2024 12:45:20 PM

NON-CONFORMANCE Region NSW1 Friday, 8 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 8 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 08/11/2024 12:30 to 08/11/2024 12:45
Amount: 16 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120139RESERVE NOTICE08/11/2024 10:45:34 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120135 has been updated at 1040 hrs to the following:

[1.] From 1800 hrs 08/11/2024 to 1930 hrs 08/11/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 951 MW.

Manager NEM Real Time Operations
     