Market Notices

118489GENERAL NOTICE27/09/2024 09:51:41 PM

Network Augmentation Commissioned - NSW Region - 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:

Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:

Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line

Manager NEM Real Time Operations
118474RESERVE NOTICE26/09/2024 08:01:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118473 is cancelled at 2000 hrs 26/09/2024.

Manager NEM Real Time Operations
118473RESERVE NOTICE26/09/2024 06:48:28 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118472 has been updated at 1850 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 996 MW.

Manager NEM Real Time Operations
118472RESERVE NOTICE26/09/2024 06:15:18 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118471 has been updated at 1815 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 726 MW.

Manager NEM Real Time Operations
118471RESERVE NOTICE26/09/2024 04:41:23 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1440 MW
The minimum capacity reserve available is 1027 MW

Manager NEM Real Time Operations
118443MARKET SYSTEMS25/09/2024 02:43:56 PM

CHG0098660:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
118434RESERVE NOTICE25/09/2024 01:24:21 AM

Cancellation of Actual (LOR1) condition in the SA region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 24/09/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.118433 is cancelled at 0120 hrs 25/09/2024.

Manager NEM Real Time Operations
118433RESERVE NOTICE24/09/2024 11:13:14 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 24/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2300 hrs.
The Actual LOR1 condition is forecast to exist until 0200 hrs

The capacity reserve requirement is 600 MW
The minimum capacity reserve available is 520 MW

Manager NEM Real Time Operations
118427GENERAL NOTICE24/09/2024 03:38:49 PM

Network Augmentation Commissioned - NSW Region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 24/09/2024

At 1535 hrs Buronga - Redcliffs X1 220 kV line has been commissioned.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm