NEM Local Temperature Alerts for SA, VIC from 11 Dec 2024 to 15 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 15th Dec
Clare High School (39+ Deg C): 15th Dec
Port Augusta Ap (39+ Deg C): 14th Dec, 15th Dec
VIC
Mildura Ap (39+ Deg C): 15th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024
NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 December 2024
NON-CONFORMANCE QLD1 Region Monday, 9 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MIDDLSF1
Duration: 09/12/2024 10:25 to 09/12/2024 11:15
Amount: 22 MW
Constraint: NC-Q_MIDDLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 9 December 2024
NON-CONFORMANCE NSW1 Region Monday, 9 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 09/12/2024 00:40 to 09/12/2024 01:05
Amount: 7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 9 December 2024
NON-CONFORMANCE NSW1 Region Sunday, 8 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/12/2024 23:50 to 09/12/2024 00:10
Amount: 6 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 08/12/2024
Cancellation - Forecast MSL1 - VIC Region at 1230 hrs 08/12/2024.
Refer to Market Notice 121617 for Forecast MSL1.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024
Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024
Update to Market Notice 121508 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 08/12/2024.
Minimum regional demand is forecast to be 1299 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1560 MW
o MSL2 - 1060 MW
o MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1130 hrs 08/12/2024 to 1400 hrs 08/12/2024.
Manager NEM Real Time Operations