Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121876 has been updated at 0510 hrs 14/12/2024 to the following:
From 1600 hrs to 2100 hrs 16/12/2024.
The forecast capacity reserve requirement is 1048 MW.
The minimum capacity reserve available is 517 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121839 has been updated at 0510 hrs 14/12/2024 to the following:
From 1600 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1058 MW.
The minimum capacity reserve available is 355 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1600 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 1103 MW.
The minimum capacity reserve available is 710 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202412131845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 18:45
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 13 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Refer to market notice: 121856
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 13 December 2024.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Friday, 13 December 2024
NON-CONFORMANCE QLD1 Region Friday, 13 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412131520_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 15:20
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1520 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412131500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 December 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 13 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Refer to market notice: 121844
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 13 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412131330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 13 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121820 has been updated at 1200 hrs 13/12/2024 to the following:
From 1600 hrs to 2030 hrs 17/12/2024.
The forecast capacity reserve requirement is 1044 MW.
The minimum capacity reserve available is 84 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations