Market Notices

121876RESERVE NOTICE13/12/2024 09:08:51 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1600 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 1103 MW.
The minimum capacity reserve available is 710 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121850RESERVE NOTICE13/12/2024 03:40:08 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121792 has been updated at 1400 hrs 13/12/2024 to the following:

1. From 1400 hrs to 1600 hrs 17/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 745 MW.

2. From 2030 hrs to 2300 hrs 17/12/2024.
The forecast capacity reserve requirement is 1849 MW.
The minimum capacity reserve available is 1119 MW.

AEMO Operations
     
121849RESERVE NOTICE13/12/2024 03:36:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121791 has been updated at 1400 hrs 13/12/2024 to the following:

From 1530 hrs to 2130 hrs 16/12/2024.
The forecast capacity reserve requirement is 1395 MW.
The minimum capacity reserve available is 710 MW.

AEMO Operations
     
121848RESERVE NOTICE13/12/2024 03:33:36 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 121795 has been updated at 1400 hrs 13/12/2024 to the following:

From 1630 hrs to 1730 hrs 16/12/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 1031 MW.

AEMO Operations
     
121847RESERVE NOTICE13/12/2024 03:30:39 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121793 is cancelled at 1400 hrs 13/12/2024.

AEMO Operations
     
121846RESERVE NOTICE13/12/2024 03:26:59 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121794 is cancelled at 1400 hrs 13/12/2024.

AEMO Operations
     
121845RESERVE NOTICE13/12/2024 03:21:37 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 121796 is cancelled at 1400 hrs 13/12/2024.

AEMO Operations
     
121842GENERAL NOTICE13/12/2024 01:14:02 PM

CORRECTION: Update - Vulnerable lines in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in QLD region

Refer to AEMO Electricity Market Notice 121840

Fix typo: Line 7141 should read Line 7143

At 2026 hrs 12/12/2024 the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 tripped.

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7143 to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
121840GENERAL NOTICE13/12/2024 01:07:46 PM

Update - Vulnerable lines in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in QLD region

Refer to AEMO Electricity Market Notice 121806

At 2026 hrs 12/12/2024 the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7141 tripped.

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers the Kamerunga to Barron Gorge 132 kV Line 7184 and the Kamerunga to Barron Gorge 132 kV Line 7141 to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     