Market Notices

121766MARKET INTERVENTION12/12/2024 09:31:31 AM

Cancellation - AEMO Intervention Event - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/12/2024

Refer to Market Notice 121721

The AEMO Intervention Event and all associated directions are cancelled from 0930 hrs on 12/12/2024.


Manager NEM Real Time Operations
     
121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121760RESERVE NOTICE12/12/2024 09:04:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:

From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121734RESERVE NOTICE12/12/2024 12:42:05 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.

[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121726SETTLEMENTS RESIDUE11/12/2024 07:20:27 PM

[EventId:202412111920_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 December 2024 19:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 11 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 December 2024.

Refer to market notice: 121724

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1920 hrs on 11 December 2024.

This is an AEMO autogenerated Market Notice.
     
121724SETTLEMENTS RESIDUE11/12/2024 05:00:34 PM

[EventId:202412111700_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 December 2024 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 11 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1700 hrs on 11 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
121722MARKET INTERVENTION11/12/2024 04:07:36 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121721


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 11/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 12/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0930 hrs 12/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
121721MARKET INTERVENTION11/12/2024 04:05:19 PM

Direction - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 11/12/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 11/12/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
121718MARKET INTERVENTION11/12/2024 03:03:55 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 121714

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 11/12/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm