121330PRICES SUBJECT TO REVIEW01/12/2024 05:20:19 PM

[EventId:202412011725_review] Prices for interval 01-Dec-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 1 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 01-Dec-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121329PRICES SUBJECT TO REVIEW01/12/2024 05:15:15 PM

[EventId:202412011720_review] Prices for interval 01-Dec-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 1 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 01-Dec-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121328PRICES SUBJECT TO REVIEW01/12/2024 05:10:19 PM

[EventId:202412011715_review] Prices for interval 01-Dec-2024 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 1 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 01-Dec-2024 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121327PRICES SUBJECT TO REVIEW01/12/2024 05:05:24 PM

[EventId:202412011710_review] Prices for interval 01-Dec-2024 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 1 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 01-Dec-2024 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121326PRICES SUBJECT TO REVIEW01/12/2024 05:00:16 PM

[EventId:202412011705_review] Prices for interval 01-Dec-2024 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 1 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 01-Dec-2024 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121309RESERVE NOTICE01/12/2024 10:44:51 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 1040 hrs 01/12/2024 to the following:

[1.] From 1630 hrs 02/12/2024 to 1700 hrs 02/12/2024.
The forecast capacity reserve requirement is 968 MW.
The minimum capacity reserve available is 732 MW.

[2.] From 1730 hrs 02/12/2024 to 1830 hrs 02/12/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 833 MW.

AEMO is seeking a market response.


AEMO Operations
     
121306RESERVE NOTICE01/12/2024 09:10:42 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121302 has been updated at 0900 hrs 01/12/2024 to the following:

[1.] From 1600 hrs 02/12/2024 to 1900 hrs 02/12/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 762 MW.

AEMO is seeking a market response.


AEMO Operations
     
121302RESERVE NOTICE30/11/2024 08:51:11 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 02/12/2024 to 1730 hrs 02/12/2024.
The forecast capacity reserve requirement is 1330 MW.
The minimum capacity reserve available is 1071 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121250PRICES SUBJECT TO REVIEW29/11/2024 03:45:16 PM

[EventId:202411291550_review] Prices for interval 29-Nov-2024 15:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     