Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121734 has been updated at 0800 hrs 12/12/2024 to the following:
From 1500 hrs to 1930 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 733 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024
NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector.
The following constraint set was invoked at 0130 hrs 12/12/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.
[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024
NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1, N-Q_MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations