Market Notices

121741PRICES SUBJECT TO REVIEW12/12/2024 01:40:21 AM

[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121740PRICES SUBJECT TO REVIEW12/12/2024 01:35:21 AM

[EventId:202412120140_review] Prices for interval 12-Dec-2024 01:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0135 hrs on 12 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121736RESERVE NOTICE12/12/2024 12:55:44 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 578 MW.
The minimum capacity reserve available is 207 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121735RESERVE NOTICE12/12/2024 12:40:55 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1500 hrs 16/12/2024 to 1530 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 295 MW.

[2.] From 1600 hrs 16/12/2024 to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 40 MW.

[3.] From 1830 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121729RESERVE NOTICE11/12/2024 08:46:54 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1500 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 755 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121723RESERVE NOTICE11/12/2024 04:03:08 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121711 has been updated at 1500 hrs 11/12/2024 to the following:

1. From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 690 MW.

2. From 1630 hrs 16/12/2024 to 1930 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 292 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121711RESERVE NOTICE11/12/2024 11:56:42 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121709 has been updated at 1100 hrs 11/12/2024 to the following:

1. From 1700 hrs to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 391 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121709RESERVE NOTICE11/12/2024 04:35:58 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121705 has been updated at 0425 hrs 11/12/2024 to the following:

[1.] From 1730 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 663 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
121705RESERVE NOTICE10/12/2024 07:14:31 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121694 has been updated at 1900 hrs 10/12/2024 to the following:

[1.] From 1700 hrs 16/12/2024 to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 318 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm