Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 01/12/2024 17:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 121315
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412011710_confirmed] Prices for interval 01-Dec-2024 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:10.
In accordance with Market Notice 121327 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011735_confirmed] Prices for interval 01-Dec-2024 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:35.
In accordance with Market Notice 121337 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011730_confirmed] Prices for interval 01-Dec-2024 17:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:30.
In accordance with Market Notice 121332 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011725_confirmed] Prices for interval 01-Dec-2024 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:25.
In accordance with Market Notice 121330 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011720_confirmed] Prices for interval 01-Dec-2024 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:20.
In accordance with Market Notice 121329 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011715_confirmed] Prices for interval 01-Dec-2024 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:15.
In accordance with Market Notice 121328 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412011705_confirmed] Prices for interval 01-Dec-2024 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 1 December 2024
PRICES ARE NOW CONFIRMED for trading interval 01-Dec-2024 17:05.
In accordance with Market Notice 121326 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Cancellation time: 01/12/2024 17:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 121321
Auto-generated on behalf of Manager NEM Real Time Operations