STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 02/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1700 hrs 02/12/2024 to 1730 hrs 02/12/2024.
The forecast capacity reserve requirement is 1330 MW.
The minimum capacity reserve available is 1071 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
A planned outage of Red Cliffs - Wemen 220 kV line in the VIC region was scheduled from 0400 hrs 30/11/2024 to 1430 hrs 30/11/2024.
The outage has been completed and Red Cliffs - Wemen 220 kV line returned to service at 1120 hrs 30/11/2024
Constraint set(s) revoked: V-KG_WE_RC
Manager NEM Real Time Operations
[EventId:202411291550_review] Prices for interval 29-Nov-2024 15:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411291545_review] Prices for interval 29-Nov-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411291540_review] Prices for interval 29-Nov-2024 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411291530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 November 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 November 2024.
Refer to market notice: 121235
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 29 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411291535_review] Prices for interval 29-Nov-2024 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411291530_review] Prices for interval 29-Nov-2024 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411291525_review] Prices for interval 29-Nov-2024 15:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 29 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.