Filter by category
Filter by Date
[EventId:202412120200_review] Prices for interval 12-Dec-2024 02:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0155 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 02:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120155_review] Prices for interval 12-Dec-2024 01:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0150 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120150_review] Prices for interval 12-Dec-2024 01:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0145 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120145_review] Prices for interval 12-Dec-2024 01:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0140 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412120140_review] Prices for interval 12-Dec-2024 01:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0135 hrs on 12 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 12-Dec-2024 01:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:
[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 578 MW.
The minimum capacity reserve available is 207 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1500 hrs 16/12/2024 to 1530 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 295 MW.
[2.] From 1600 hrs 16/12/2024 to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 40 MW.
[3.] From 1830 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 16/12/2024 to 2000 hrs 16/12/2024.
The forecast capacity reserve requirement is 755 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202412111920_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 December 2024 19:20
Issued by Australian Energy Market Operator Ltd at 1920 hrs on 11 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 December 2024.
Refer to market notice: 121724
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1920 hrs on 11 December 2024.
This is an AEMO autogenerated Market Notice.