Market Notices

120566PRICES UNCHANGED17/11/2024 04:17:58 PM

[EventId:202411171605_confirmed] Prices for interval 17-Nov-2024 16:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:05.

In accordance with Market Notice 120560 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120565PRICES UNCHANGED17/11/2024 04:15:24 PM

[EventId:202411171600_confirmed] Prices for interval 17-Nov-2024 16:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 16:00.

In accordance with Market Notice 120559 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120564PRICES UNCHANGED17/11/2024 04:16:48 PM

[EventId:202411171550_confirmed] Prices for interval 17-Nov-2024 15:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 17 November 2024

PRICES ARE NOW CONFIRMED for trading interval 17-Nov-2024 15:50.

In accordance with Market Notice 120557 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120561SETTLEMENTS RESIDUE17/11/2024 04:06:41 PM

[EventId:202411171605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 November 2024 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 17 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
120554MARKET INTERVENTION17/11/2024 03:59:45 PM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer AEMO Electricity Participant Notice 120529

The MINTARO MINTARO GAS direction is now expected to stay in place until 1830 hrs 18/11/2024.

The direction update is issued at 1600 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120553MARKET INTERVENTION17/11/2024 03:57:41 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120528

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/11/2024.

The direction update is issued at 1600 hrs 17/11/2024.

Manager NEM Real Time Operations
     
120530MARKET INTERVENTION16/11/2024 05:00:04 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 120527

Direction is cancelled from: 1700 hrs 16/11/2024

Manager NEM Real Time Operations
     
120529MARKET INTERVENTION16/11/2024 03:59:06 PM

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 120499


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 16/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0100 hrs 17/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 18/11/2024.

Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120528MARKET INTERVENTION16/11/2024 03:56:33 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120500

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/11/2024.

The direction update is issued at 1600 hrs 16/11/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm