[EventId:202412161715_confirmed] Prices for interval 16-Dec-2024 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:15.
In accordance with Market Notice 122027 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161710_confirmed] Prices for interval 16-Dec-2024 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:10.
In accordance with Market Notice 122026 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161705_confirmed] Prices for interval 16-Dec-2024 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:05.
In accordance with Market Notice 122024 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1297 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 17/12/2024 to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1156 MW.
The minimum capacity reserve available is 550 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121999 has been updated at 1100 hrs 16/12/2024 to the following:
From 1500 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 444 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121995 has been updated at 1000 hrs 16/12/2024 to the following:
From 1500 hrs to 1930 hrs 17/12/2024.
The forecast capacity reserve requirement is 1164 MW.
The minimum capacity reserve available is 133 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NEM Local Temperature Alerts for SA, VIC from 16 Dec 2024 to 20 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Clare High School (39+ Deg C): 16th Dec
Port Augusta Ap (39+ Deg C): 16th Dec
VIC
Ararat Prison (39+ Deg C): 16th Dec
Latrobe Valley Ap (39+ Deg C): 16th Dec
Melbourne Olympic Park (39+ Deg C): 16th Dec
Mildura Ap (39+ Deg C): 16th Dec, 20th Dec
Mortlake (39+ Deg C): 16th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121960 has been updated at 0800 hrs 16/12/2024 to the following:
From 1500 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1012 MW.
The minimum capacity reserve available is 408 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.