118736INTER-REGIONAL TRANSFER09/10/2024 07:58:20 PM

Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool to Sydenham 500 kV No.2 line - VIC region - 09/10/2024

A planned outage of Moorabool to Sydenham 500 kV No.2 line in the VIC region was scheduled from 0600 hrs 01/10/2024 to 2030 hrs 11/10/2024.

The outage has been completed and Moorabool to Sydenham 500 kV No.2 line returned to service at 1940 hrs 09/10/2024

Constraint set(s) revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     
118693NON-CONFORMANCE09/10/2024 08:40:22 AM

NON-CONFORMANCE Region SA1 Wednesday, 9 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 9 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MANNSF2
Duration: 09/10/2024 08:15 to 09/10/2024 08:40
Amount: 25 MW
Constraint: NC-S_MANNSF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118668NON-CONFORMANCE08/10/2024 10:05:23 AM

NON-CONFORMANCE Region NSW1 Tuesday, 8 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 8 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 08/10/2024 10:00 to 08/10/2024 10:05
Amount: -37 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
118663NON-CONFORMANCE07/10/2024 03:12:48 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 13:25 to 07/10/2024 15:10
Amount: 62 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118643NON-CONFORMANCE07/10/2024 01:10:15 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 11:25 to 07/10/2024 13:10
Amount: 101 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118638NON-CONFORMANCE07/10/2024 10:15:28 AM

NON-CONFORMANCE Region NSW1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WAGGNSF1
Duration: 07/10/2024 09:55 to 07/10/2024 10:15
Amount: 49 MW
Constraint: NC-N_WAGGNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118635NON-CONFORMANCE06/10/2024 11:32:58 PM

NON-CONFORMANCE Region SA1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LKBONNY2
Duration: 06/10/2024 23:05 to 06/10/2024 23:10
Amount: 73 MW
Constraint: NC-S_LKBONNY2

Manager NEM Real Time Operations
     
118631NON-CONFORMANCE06/10/2024 01:25:28 PM

NON-CONFORMANCE Region NSW1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 06/10/2024 13:00 to 06/10/2024 13:25
Amount: 9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118627NON-CONFORMANCE06/10/2024 08:20:19 AM

NON-CONFORMANCE Region QLD1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/10/2024 20:05 to 06/10/2024 08:20
Amount: -56 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     