STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120614 has been updated at 1400 hrs 19/11/2024 to the following:
1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1930 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 927 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2000 hrs 26/11/2024.
The forecast capacity reserve requirement is 1347 MW.
The minimum capacity reserve available is 833 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1230 hrs to 1430 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 891 MW.
2. From 2030 hrs to 2330 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1900 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1259 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1430 hrs to 1600 hrs 26/11/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 110 MW.
2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 77 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202411191435_review] Prices for interval 19-Nov-2024 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 19 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411191430_review] Prices for interval 19-Nov-2024 14:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1425 hrs on 19 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 14:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411191425_review] Prices for interval 19-Nov-2024 14:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1420 hrs on 19 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 14:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411191420_review] Prices for interval 19-Nov-2024 14:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 19 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 14:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.