Network Augmentation Commissioned - VIC Region - 07/08/2024
Network Augmentation Commissioned - VIC Region - 07/08/2024
Cressy - Golden Plains No. 2 220 kV Line has been commissioned.
Manager NEM Real Time Operations
[EventId:202408051640_confirmed] Prices for interval 05-Aug-2024 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:40.
In accordance with Market Notice 117549 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051700_confirmed] Prices for interval 05-Aug-2024 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 17:00.
In accordance with Market Notice 117553 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051655_confirmed] Prices for interval 05-Aug-2024 16:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:55.
In accordance with Market Notice 117552 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051650_confirmed] Prices for interval 05-Aug-2024 16:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:50.
In accordance with Market Notice 117551 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051645_confirmed] Prices for interval 05-Aug-2024 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:45.
In accordance with Market Notice 117550 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051635_confirmed] Prices for interval 05-Aug-2024 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:35.
In accordance with Market Notice 117548 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.
The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024
Constraint set(s) revoked: V-KTSM_R
Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade