STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112160 has been updated at 1400 hrs 11/12/2023 to the following:
From 1530 hrs to 2000 hrs 14/12/2023.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 14/12/2023.
The forecast capacity reserve requirement is 1287 MW.
The minimum capacity reserve available is 1019 MW.
AEMO Operations
CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082105 | Completed | Production | BAU Retail Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/12/2023.
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112042 has been updated at 1530 hrs 10/12/2023 to the following:
From 1600 hrs 14/12/2023 to 1830 hrs 14/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1076 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112130 has been updated at 1515 hrs to the following:
From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1132 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112083 has been updated at 0945 hrs to the following:
From 1530 hrs 09/12/2023 to 1900 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 804 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112082 is cancelled at 1700 hrs 08/12/2023.
Manager NEM Real Time Operations