CHG0082301 | Production | Planned System Maintenance - Electricity MMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS Production Bay transfer
Change Start Date & Time: 11/12/2023 13:00:00 AEST
Change End Date & Time: 13/12/2023 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The maintenance activity is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600 .
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NEM Local Temperature Alerts for VIC from 11 Dec 2023 to 15 Dec 2023
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
VIC
Mildura Ap (39+ Deg C): 12th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
CHG0081726 | Completed | Production | Renewal of webMethods ESB server certificate
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Renewal of webMethods ESB server certificate
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082105 | Completed | Production | BAU Retail Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: BAU Retail Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Network Augmentation Commissioned - SA Region - 10/12/2023
Network Augmentation Commissioned - SA Region - 10/12/2023
Commissioned: Robertstown - Bundey No. 1 275 kV Line
Bundey 275 kV Swtichyard
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 08/12/2023
Network Augmentation Commissioned - NSW Region - 08/12/2023
Commissioned: Wellington - Wellington North Solar Farm 7H 330 kV Line
Manager NEM Real Time Operations
[EventId:202312081550_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 15:50
Issued by Australian Energy Market Operator Ltd at 1550 hrs on 8 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Refer to market notice: 112094
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1550 hrs on 8 December 2023.
This is an AEMO autogenerated Market Notice.
[EventId:202312081450_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 December 2023 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 8 December 2023
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1450 hrs on 8 December 2023.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202312081120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 December 2023 11:20
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 8 December 2023
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 December 2023.
Refer to market notice: 112063
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 8 December 2023.
This is an AEMO autogenerated Market Notice.