Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112130 has been updated at 1515 hrs to the following:
From 1600 hrs 09/12/2023 to 1830 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1132 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112083 has been updated at 0945 hrs to the following:
From 1530 hrs 09/12/2023 to 1900 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 804 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 8 December 2023
NON-CONFORMANCE QLD1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SWAN_E
Duration: 08/12/2023 17:05 to 08/12/2023 17:10
Amount: 20 MW
Constraint: NC-Q_SWAN_E
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112082 is cancelled at 1700 hrs 08/12/2023.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1530 hrs 09/12/2023 to 1600 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1253 MW.
[2.] From 1830 hrs 09/12/2023 to 1900 hrs 09/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1239 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
From 1630 hrs 08/12/2023 to 1730 hrs 08/12/2023.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1070 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 December 2023
NON-CONFORMANCE NSW1 Region Friday, 8 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: SUNTPSF1
Duration: 08/12/2023 12:35 to 08/12/2023 12:50
Amount: 76 MW
Constraint: NC-N_SUNTPSF1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/12/2023
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 112052 is cancelled at 0515 hrs 08/12/2023.
Manager NEM Real Time Operations