NON-CONFORMANCE Region QLD1 Friday, 20 September 2024
NON-CONFORMANCE QLD1 Region Friday, 20 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 18:10 to 20/09/2024 18:25
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 20 September 2024
NON-CONFORMANCE QLD1 Region Friday, 20 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 17:15 to 20/09/2024 17:40
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024
NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024
NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation -South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
Inter-regional transfer limit variation - South East to Tailem Bend No 1 275 KV Line - SA region - 17/09/2024
At 1034 hrs 17/09/2024 there was a short notice outage of South East to Tailem Bend No 1 275 KV Line.
The following constraint set(s) invoked at 1035 hrs 20/09/2024
S-TBSE,
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,NSW1-QLD1,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
Inter-regional transfer limit variation - Braemar No2 330 kV / 275 kV Transformer. - QLD region - 14/09/2024
At 1320 hrs 14/09/2024 there was a short notice outage of Braemar No2 330 kV / 275 kV Transformer.
The following constraint set(s) invoked at 1320 hrs 14/09/2024
Q-BRTX2
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.
The outage has been completed and Armidale - Sapphire 8E 330 KV Line returned to service at 1600 hrs 13/09/2024
Constraint set(s) revoked: N-ARSR_8E, N-TW_SVC
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 KV Line - NSW region - 13/09/2024
A planned outage of Armidale - Sapphire 8E 330 KV Line in the NSW region was scheduled from 1630 hrs 11/09/2024 to 1330 hrs 13/09/2024.
The outage has been rescheduled for 1630 hrs 11/09/2024 to 1330 hrs 14/09/2024.
Constraint sets invoked: N-ARSR_8E, N-TW_SVC, N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024
Inter-regional transfer limit variation - Murraylink - SA region - 12/09/2024
A planned outage of Murraylink in the SA region was scheduled from 1030 hrs 12/09/2024 to 1630 hrs 12/09/2024.
The outage has been completed and Murraylink returned to service at 1235 hrs 12/09/2024
Constraint set(s) revoked: I-MURRAYLINK