117904GENERAL NOTICE27/08/2024 05:00:48 PM

Network Augmentation Commissioned - VIC Region - 27/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 27/08/2024

Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.

Manager NEM Real Time Operations
117889MARKET SYSTEMS27/08/2024 03:33:37 PM

CHG0095127 | Completed | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Change Number: CHG0095127
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117875MARKET SYSTEMS27/08/2024 02:34:03 PM

CHG0096175 | Production | EMMS Production Bay transfer

Change Number: CHG0096175
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer

Change Start Date & Time: 02/09/2024 09:00:00 AEST
Change End Date & Time: 04/09/2024 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: EMMS Bay transfer is scheduled for 3rd September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.

117809MARKET SYSTEMS26/08/2024 09:49:57 AM

CHG0095221 | Cancelled | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0095221
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: Gas Hub

Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117808MARKET SYSTEMS26/08/2024 09:47:55 AM

CHG0091459 | Cancelled | Production | MSATS CATS & URM Site Transfer BNE to NOR Data Centre

Change Number: CHG0091459
Notification issued to: Market Notice

Notification Type: Cancelled
Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: MSATS CATS & URM Site Transfer BNE to NOR Data Centre

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117761MARKET SYSTEMS23/08/2024 01:18:42 PM

CHG0095127 | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Change Number: CHG0095127
Notification issued to: Market Notice

Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Change Start Date & Time: 27/08/2024 13:00:00 AEST
Change End Date & Time: 27/08/2024 17:00:00 AEST
Outage Start Date & Time: 27/08/2024 13:00:00 AEST
Outage End Date & Time: 27/08/2024 17:00:00 AEST

Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
117740MARKET SYSTEMS21/08/2024 10:52:48 AM

CHG0095739 | Cancelled | Production | AEMO will be undertaking maintenance activities on the system.

Change Number: CHG0095739

Notification issued to: Market Notice

Notification Type: Cancelled

Change Type: Normal

Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the system.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
117739MARKET SYSTEMS21/08/2024 10:50:59 AM

CHG0093465 | Completed | Production | AEMO will be undertaking maintenance activities on the STTM system.

Change Number: CHG0093465

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the STTM system.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

117738MARKET SYSTEMS21/08/2024 10:46:35 AM

CHG0095840 | Completed | Production | AEMO will be undertaking maintenance activities on the DWGM system

Change Number: CHG0095840

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the DWGM system

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm