NON-CONFORMANCE Region QLD1 Thursday, 29 August 2024
NON-CONFORMANCE QLD1 Region Thursday, 29 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE2
Duration: 29/08/2024 15:35 to 29/08/2024 15:40
Amount: 28 MW
Constraint: NC-Q_GSTONE2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 28/08/2024
Update - Non-credible contingency event - VIC region - 28/08/2024
Refer AEMO Electricity Market Notice 117908
At 0134 hrs the APD No 2 Potline was returned to service.
At 0200 hrs the APD No 1 Potline was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 28/08/2024
Non-credible contingency event - VIC region - 28/08/2024
At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 25/08/2024
Update - Non-credible contingency event - TAS region - 25/08/2024
Refer AEMO Electricity Market Notice 117782
At 1023 hrs the New Norfolk A 110kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 25/08/2024
Non-credible contingency event - TAS region - 25/08/2024
At 0850 hrs the New Norfolk A 110kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 24 August 2024
NON-CONFORMANCE NSW1 Region Saturday, 24 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WYASF1
Duration: 24/08/2024 11:10 to 24/08/2024 11:20
Amount: 43 MW
Constraint: NC-N_WYASF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 23 August 2024
NON-CONFORMANCE NSW1 Region Friday, 23 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: CAPBES1G, CAPBES1L
Aggregate Dispatch Group: CBESS_ADG1
Duration: 23/08/2024 04:35 to 23/08/2024 05:00
Amount: 13 MW
Constraint: NC-N_CBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 21 August 2024
NON-CONFORMANCE QLD1 Region Wednesday, 21 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 21/08/2024 21:50 to 21/08/2024 22:00
Amount: 10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 15 August 2024
NON-CONFORMANCE QLD1 Region Thursday, 15 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 15/08/2024 22:25 to 15/08/2024 22:50
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations